SUPPORT SERVICES CENTER


Project Scope
The Support Services facility project will provide space to expand and relocate Purchasing & Materials Management, Food Service Support, Maintenance & Operations and Graphic Arts.

Construction Budget
$9,504,000.00

Vanir - Rice & Gardner Team
Dean Lanuke - Project Manager
Dustin Fredrickson - Asst. Project Manager

Project Architect
PBK Architects

General Contractor
C.A. Walker Construction

Schedule Milestones

Maintenance & Operaions Building:
Current Phase: Construction
Contruction Start: May 30, 2017
Contract Completion: April 2018

Support Services Facility:
Current Phase: Construction
Construction Start: May 2018
Contract Completion: October 2018

Current Status - March 2018

Maintenance & Operations Building:

  • Construction is 98% complete.

  • Painting of interior walls is complete.

  • Exterior cement board is installed in office wing and has been painted.

  • Casework installation is complete.

  • Restroom fixtures installation is complete.

  • Technology installation is complete.







 
 