SUPPORT SERVICES CENTER


Project Scope
The Support Services facility project will provide space to expand and relocate Purchasing & Materials Management, Food Service Support, Maintenance & Operations and Graphic Arts.

Construction Budget
$9,504,000.00

Vanir - Rice & Gardner Team
Dean Lanuke - Project Manager
Dustin Fredrickson - Asst. Project Manager

Project Architect
PBK Architects

General Contractor
C.A. Walker Construction

Schedule Milestones

Maintenance & Operaions Building:
Current Phase: Construction
Contruction Start: May 30, 2017
Contract Completion: February 2018

Support Services Facility:
Current Phase: Construction
Construction Start: March 2018
Contract Completion: September 2018

Current Status - October 2017

Maintenance & Operations Building:

  • Site utility work is underway.

  • Structural concrete foundation is complete.

  • Building slab has been poured.

  • Parking and drives are being prepared with lime stabilization for added strength.


 
 