Site Lighting - District Wide

Project Scope
Upgrade of Site Lighting

Construction Budget
$900,000.00

Vanir - Rice & Gardner Team
Dustin Fredrickson - Project Manager

Project Engineer
KCI Technologies, Inc.

General Contractor
Siemens Industry, Inc.

Schedule Milestones

  • Current Phase: Construction

  • Construction Start: 4th Quarter 2017

  • Construction Completion: 2nd Quarter 2018


Current Status - May 2018

  • Original scope of work is complete.

  • Final inspections and night audits to confirm all lights are operating is underway.

  • Phase 2 sites have been added and additional light fixtures have been ordered.







 
 