Projects > Construction

Site Lighting - District Wide

Project Scope
Upgrade of Site Lighting

Construction Budget
$900,000.00

Vanir - Rice & Gardner Team
Dustin Fredrickson - Project Manager

Project Engineer
KCI Technologies, inc.

Schedule Milestones

  • Current Phase: Construction Documents

  • Construction Start: 3rd Quarter 2017

  • Construction Completion: 4th Quarter 2017

Current Status - July 2017

  • Parking lot lighting and exterior building wall lights will be replaced at 46 school and support sites.

  • 17 cost proposals were received on July 25, 2017.

  • Contractor qualifications are being evaluated to make a recommendation for award in August.


 
 