Site Lighting - District Wide

Project Scope
Upgrade of Site Lighting

Construction Budget
$900,000.00

Vanir - Rice & Gardner Team
Dustin Fredrickson - Project Manager

Project Engineer
KCI Technologies, Inc.

General Contractor
Siemens Industry, Inc.

Schedule Milestones

  • Current Phase: Construction

  • Construction Start: 4th Quarter 2017

  • Construction Completion: 2nd Quarter 2018


Current Status - October 2017

  • Parking lot lighting and exterior building wall lights will be replaced at 46 schools and support sites.

  • Contractor is verifying lighting fixtures for placing order.

  • Replacement of light fixtures is scheduled to begin in December.

 
 