Site Lighting - District Wide

Project Scope
Upgrade of Site Lighting

Construction Budget
$900,000.00

Vanir - Rice & Gardner Team
Dustin Fredrickson - Project Manager

Project Engineer
KCI Technologies, Inc.

General Contractor
Siemens Industry, Inc.

Schedule Milestones

  • Current Phase: Construction

  • Construction Start: 4th Quarter 2017

  • Construction Completion: 2nd Quarter 2018


Current Status - March 2018

  • Original scope of replacing exterior pole lights and wall pack lights with new LED light fixtures is complete.

  • 1,669 light fixtures have been replaced across the District.

  • Final inspections are underway.





 
 