PRACTICE POOLS

George Ranch High School
Foster High School
Fulshear High School

Project Scope
Construction of 3 new practice pool facilities.

Construction Budget
$7,150,000.00

Vanir - Rice & Gardner Team
Douglas Walker-Rice - Project Manager


Project Architect
PBK Architects

General Contractor
Turner Construction

Schedule Milestones
Current Phase: Construction
Construction Start: 3rd Quarter 2017
Construction Completion: 3rd Quarter 2018

Current Status - July 2017

  • Contractor has mobilized on all sites.

  • Construction fencing has been put up at all three sites.

  • Site coordination has been completed to direct traffic around the construction work.


 
 