Project Scope
The Support Services facility project will provide space to expand and relocate Purchasing & Materials Management, Food Service Support, Maintenance & Operations and Graphic Arts.

Construction Budget
$9,504,000.00

Vanir - Rice & Gardner Team
Dean Lanuke - Project Manager
Dustin Fredrickson - Asst. Project Manager

Project Architect
PBK Architects

General Contractor
C.A. Walker Construction

Schedule Milestones
Current Phase: Warranty
Contruction Start: May 30, 2017
Contract Completion: April 2018

Current Status - September 2018

  • Warranty corrections being addressed.











 
 