KATHLEEN JOERGER LINDSEY ELEMENTARY
2431 Joan Collier Trace
Katy, TX 77494

Project Scope
New Elementary School for 750 students.

Construction Budget
$19,093,061.00

Vanir - Rice & Gardner Team
Dean Lanuke - Senior Project Manager
Robbie Hausler - Construction Manager
Dustin Fredrickson - Asst. Project Manager

Project Arcitecht
PBK Architects

General Contractor
Drymalla Construction Company, Inc.

Schedule Milestones

  • Current Phase: Punch List

  • Construction Start: April 22, 2016

  • Contract Completion: June 23, 2017


Current Status - July 2017

  • The punch list is being completed

  • Closeout Documents are being reviewed


 
 