HVAC Web Controls

Project Scope
Upgrade of HVAC Conrols.

Construction Budget
$900,000.00

Vanir - Rice & Gardner Team
Rod Sias - Project Manager

Project Engineer
Estes, McClure & Associates, Inc.

Schedule Milestones
Current Phase: Construction
Construction Start: July 18, 2017
Construction Completion: January 19, 2018

Current Status - July 2017

  • Additional data drops are being installed to communicate with the new controls.

  • Currently replacing controls at Foster High School, Central Plant, and Briscoe Junior High School before school starts.


 
 