Fulshear HS Shell

Project Scope

Construction Budget
$2,983,781.00

Vanir-Rice & Gardner Team
Dean Lanuke - Senior Project Manager

Project Arcitecht
PBK Architects

Schedule Milestones
Current Phase: Construction
Construction Start: May 2018
Contract Completion: August 2018

Current Status - April 2018

  • Construction is 10% complete.

  • Interior walls have been installed with sheetrock in all areas.

  • HVAC ductwork has been installed.

  • Electrical conduit installation is underway.





 
 