Don Carter Elementary School


Project Scope
New Elementary School for 750 students.

Construction Budget
$20,047,714.00

Vanir - Rice & Gardner Team
Dean Lanuke - Senior Program Manager
Robbie Hausler - Construction Manager
Dustin Fredrickson - Asst. Program Manager


Project Architect
VLK Architects

General Contractor
Drymalla Construction Company, Inc.

Schedule Milestones
Current Phase: Construction
Construction Start: May 30,
2017
Contract Completion: July 21, 2018

Current Status - March 2018

  • Construction is 65% complete.

  • Roofing is 95% complete.

  • Exterior wall masonry is 95% complete.

  • Mechanical, Electrical and Plumbing is progressing.

  • Interior drywall is progressing.

  • Sidewalks are being poured.

  • Ceiling grid is being installed.






 
 