Don Carter Elementary School


Project Scope
New Elementary School for 750 students.

Construction Budget
$20,047,714.00

Vanir - Rice & Gardner Team
Dean Lanuke - Senior Program Manager
Robbie Hausler - Construction Manager
Dustin Fredrickson - Asst. Program Manager


Project Architect
VLK Architects

General Contractor
Drymalla Construction Company, Inc.

Schedule Milestones
Current Phase: Construction
Construction Start: May 30,
2017
Contract Completion: July 21, 2018

Current Status - October 2017

  • Construction is 19% complete.

  • Underground utility work is progressing for CenterPoint electric connection.

  • Concrete driveways and parking areas are being poured.

  • Structural steel erection has begun.

  • Roof decking has started in areas A & B.

  • Exterior wall frame has started.

  • Electrical wiring has begun in area A & B.

  • Widening of A Meyer Rd. is in progress.


 
 