CARL BRISCOE BENTLY ELEMENTARY SCHOOL
9910 FM 359
Richmond, TX 77406

Project Scope
New Elementary School for 750 students.

Construction Budget
$18,946,904.00

Vanir - Rice & Gardner Team
Dean Lanuke - Senior Project Manager
Robbie Hausler - Construction Manager
Douglas Walker-Rice - Asst. Project Manager

Project Architect
PBK Architects

General Contractor
Gamma Construction

Schedule Milestones
Current Phase: Close Out
Construction Start: October 16, 2015
Moved In: December 30, 2016

First Day of School: January 3, 2017

Current Status - July 2017

  • The punch list is complete.

  • Closeout documents are being finalized.

  • Contractor is installing culverts and crossings at the new traffic signal to meet TxDOT requirements.


 
 