Baseball Complex

Terry High School
5500 Avenue N
Rosenberg, TX 77471

Project Scope
Phase 1 of a two phased master plan:  Design and construction of new dugouts, fencing, ticket booth, concession booth, restrooms, drainage, lighting upgrades, replacement or treatment of wood light poles on the softball field, and upgrades to the baseball and softball fencing and fields.

Construction Budget
$2,000,000.00

Vanir - Rice & Gardner Team
Florentina Ganem - Project Manager

Project Architect
PBK Architects

General Contractor
Millis Development and Contsruction, LLC

Schedule Milestones
Current Phase: Close-Out
Construction Start: 3rd Quarter 2017
Construction Completion: February 2018

Current Status - March 2018

  • All construction is complete.

  • Final Punch List work is nearing completion.






 
 