BAND HALL EXPANSIONS

Lamar Consolidated High School
Terry High School


Project Scope
Design and construction of a one story 1,500 sf addition of the existing band hall that will be used for a separate rehearsal space.

Construction Budget
$500,000.00

Vanir - Rice & Gardner Team
Florentina Ganem - Project Manager

Project Architect
VLK Architects

General Contractor
IKLO Construction

Schedule Milestones
Current Phase: Punch List
Construction Start: 2nd Quarter 2017
Construction Completion: April 2018

Current Status - May 2018
Lamar CHS and Terry HS:

  • Currently working on Punch List items.








 
 