HVAC Web Controls

Project Scope
Upgrade of HVAC Conrols.

Construction Budget
$900,000.00

Vanir - Rice & Gardner Team
Rod Sias - Project Manager

Project Engineer
KCI Technologies, inc.

Schedule Milestones
Current Phase: Construction Documents
Construction Start: 4th Quarter 2017
Construction Completion: 1st Quarter 2018

Current Status - July 2017

  • Building plans have been completed to identify the doors to receive card access.

  • Construction Documents are being finalized in preparation for soliciting contractor proposals.



 
 